Laytime day counting conventions are the terms of a voyage charter that decide which days or hours count against the time allowed to load or discharge once laytime has started. The conventions are written as abbreviations, such as SHEX or WWD, and they combine, with the rules on reversible and averaged laytime, to fix the length of the time allowed before demurrage begins.
Laytime starts after the vessel is ready and a notice of readiness has been accepted, under the rules of the commencement clauses. The conventions here then decide how time runs: either continuously, as with running days, or with exceptions for weather, weekends and holidays. Other stoppages are dealt with under Laytime Exceptions and Time Counting Rules, and the result is calculated from the voyage records. Every example below uses laytime of four days starting on a Friday at 00:00, and a comparison appears at the end.
Running Days
Running days are consecutive calendar days, counted from midnight to midnight, including Sundays and holidays, with nothing excepted. Laytime of five running days from Friday 08:00 therefore ends 120 hours later, on Wednesday at 08:00. A related form, running hours, counts the allowance in hours without regard to the calendar.
Running days produce the longest continuous clock and the least argument, since weather and weekends do not interrupt it. They are used where the port works continuously, as in many bulk terminals. Time counts even if the work is stopped, unless another clause says otherwise, in contrast to weather working days, where time lost to bad weather is excluded. For four running days from Friday 00:00, laytime ends at midnight on Monday.
Weather Working Day (WWD)
A weather working day is a working day on which the weather permits cargo work. Days or parts of days when work is prevented by weather, such as rain for a grain cargo, do not count as laytime. A weather working day may be defined as a period of 24 consecutive hours, which is the form most used in dry bulk, or as a calendar day. Rates in the contract, under cargo handling rate clauses, are often given per weather working day, with the abbreviation PWWD, for example 10,000 tonnes PWWD.
In the usual approach, time lost to weather is deducted, so a day with 12 hours of rain counts as half a day. The term is often combined with SHEX, written WWD SHEX, so that Sundays and holidays also do not count. Proof of the weather stoppage comes from the master's log and the statement of facts. The effect is a longer laytime in calendar terms and less risk of demurrage for the charterer.
Weather Permitting (WP)
Weather permitting is a qualifier meaning that time counts as laytime only while the weather allows cargo work. It is added to working days, as in 3 working days of 24 consecutive hours weather permitting, and is close to a weather working day, though it is written as a suspension of the clock while a weather stoppage lasts instead of a definition of a day.
Example: laytime of three working days starts on Monday at 08:00 and rain stops work on Tuesday from 10:00 to 16:00. Three days equal 72 hours, which would end on Thursday at 08:00, but the six hours lost do not count, so laytime ends on Thursday at 14:00. Evidence comes from the master's log and the statement of facts, and disputes usually turn on whether the weather really prevented work, not merely made it slower.
Sundays and Holidays Excepted (SHEX)
Sundays and holidays excepted means that Sundays and public holidays at the port do not count as laytime. Often the words unless used are added, in which case time on an excepted day counts if loading or discharging actually takes place. Four days of laytime from Friday 00:00 run on Friday, Saturday, Monday and Tuesday, and laytime ends at midnight on Tuesday, a day later than with running days.
The exception protects the charterer against waiting time at ports where little work is done at the weekend. Under English law, once a vessel is on demurrage, excepted days still count unless the charter states otherwise, summarised as once on demurrage, always on demurrage. Where the parties intend otherwise, they add words to that effect. Holiday definitions follow the law or custom of the port, and in some places Friday replaces Sunday.
Sundays and Holidays Included (SHINC)
Sundays and holidays included means that Sundays and holidays count as laytime like any other day. The convention is used in ports and trades that work seven days a week, such as large bulk terminals, and it is sometimes agreed at a lower freight in exchange for a shorter effective period.
Four days of laytime from Friday 00:00 end at midnight on Monday, as they do with running days, so SHINC differs from SHEX by one day in this example. Charterers must work or arrange cargo at weekends or they risk demurrage, and owners prefer it because the clock runs through weekends. If the charter says working days SHINC, weekends count, while public holidays that fall on a weekday count too. The comparison below shows the full effect.
Saturdays, Sundays and Holidays Excepted (SSHEX)
Saturdays, Sundays and holidays excepted means that neither Saturdays nor Sundays nor holidays count. It is the typical five-day-week convention for ports and shippers that do not work at the weekend, such as some container-oriented or agricultural ports. Laytime starts to run again on the next working day.
With four days of laytime from Friday 00:00, time counts on Friday, Monday, Tuesday and Wednesday, so laytime ends at midnight on Wednesday. This is two days later than running days. For the shipowner the result is a longer wait, and demurrage starts later, so owners often ask for a higher rate or a shorter allowance in exchange. As with SHEX, the exception applies only until the vessel is on demurrage, and variants such as Friday and holidays excepted are used in countries where Friday is the weekly rest day.
Saturdays, Sundays and Holidays Included (SSHINC)
Saturdays, Sundays and holidays included means that all of those days count. In effect it makes laytime run continuously in the same way as running days, and the two terms are often used together or interchangeably. The longer name is used to make it clear that weekends are not excepted, in contrast to SSHEX.
Four days of laytime from Friday 00:00 end at midnight on Monday. The convention is typical for ports that work around the clock, for tanker terminals and for bulk ports with shift work, and it is also the convention preferred by owners, since it shortens the time before demurrage. Compared with SHINC, SSHINC is the more explicit form, as Saturdays are named, and the difference in practice is mostly one of wording.
Comparison of the conventions
| Convention | Days counted in the example | Laytime ends |
|---|---|---|
| Running days | Fri, Sat, Sun, Mon | Midnight Monday |
| SHINC, SSHINC | Fri, Sat, Sun, Mon | Midnight Monday |
| SHEX | Fri, Sat, Mon, Tue | Midnight Tuesday |
| SSHEX | Fri, Mon, Tue, Wed | Midnight Wednesday |