Cargo handling rate clauses are provisions of a Voyage Charter or similar contract that set the speed at which cargo must be loaded or discharged. The rate matters because it determines how many days of laytime are used. Time beyond the agreed laytime attracts Demurrage, and time saved may earn despatch, as set out in Demurrage and Despatch Clauses. The clauses are most common in dry cargo charters, including those where cargo handling costs are split under Free In and Out Cargo Handling Arrangements, and where several hatches, gangs and shore facilities can work at once.
The clauses fall into two types. Some fix a numerical rate, which turns laytime into a calculation. Others refer to a standard, such as the ship's capability or local practice, and leave the speed to be established after the event from records such as the statement of facts, described in Voyage Records for Laytime and Cargo Outturn, and the Notice of Readiness (NOR). When laytime starts is set by Laytime Commencement Clauses, day-counting rules are covered in Laytime Day Counting Conventions, and the wider contract is described under Charterparty.
Per Hatch Per Day
Per hatch per day is a laytime method in which an agreed daily rate applies to each hatch of the ship, so the time allowed grows or shrinks with the number of hatches that can be worked. Laytime is found by dividing the cargo by the rate per hatch per day multiplied by the number of hatches:
For example, 30,000 tonnes loaded at 1,500 tonnes per hatch per day through five hatches gives 30,000 divided by 7,500, or four days. Charters distinguish working hatches, meaning those through which cargo is actually loaded or discharged, from workable hatches, meaning those that could be used given the way the cargo is stowed. The wording decides which count applies, and a clause may add a cap such as a maximum number of hatches that can be worked at one time.
Fast As Can (FAC)
Fast as can (FAC) is a term meaning that the charterer, shipper or receiver must supply or take cargo as quickly as the ship can load or discharge it. Unlike a fixed-rate clause it names no figure. The obligation is measured against what the ship is capable of, subject to the limits of the port, and it does not depend on how many hours or days are allowed.
Because the rate is open, laytime cannot be calculated in advance. Where no fixed laytime exists, delay is generally claimed as damages for detention rather than as demurrage, which is an agreed sum for time beyond an agreed period. Evidence of what the ship could have achieved, including pumping or loading logs, therefore becomes central in a dispute. FAC is sometimes combined with a fixed laytime so that the rate is open but a time limit still applies.
Customary Quick Dispatch (CQD)
Customary quick dispatch (CQD) is a charterparty term obliging loading or discharge at the customary speed of the port, without a fixed number of laytime days. The standard is the speed that a diligent operator would achieve at that port, using the facilities usually available there, in the weather and conditions prevailing at the time. The phrase is also written as customary quick despatch.
As with fast as can, a claim for delay is normally a claim for damages for detention, because no agreed laytime exists to be exceeded. Disputes turn on evidence of port practice and of the facts of the particular operation, and they are commonly referred to arbitration, often in London where the charter is governed by English law. A related risk is that port congestion or equipment limits can be argued to form part of the customary speed.
Custom of the Port (COP)
Custom of the port (COP) is a fallback in charterparties: where the contract is silent on a point of loading or discharge practice, local usage at the port fills the gap. The point might be working hours, the treatment of holidays or the way cargo is handled. Under English law a custom must be proved as a fact, and it must be certain, reasonable and well known in the port. It cannot override an express term of the charter.
The effect on laytime is that periods which count, or do not count, may be settled by port custom rather than by the printed form, so owners and charterers often seek to write the rule into the contract instead. Evidence usually comes from port authority rules, agents and past voyages. See Laytime Exceptions and Time Counting Rules for the principal exclusions that an express clause normally sets out.