The loan-to-cost ratio (LTC) is a measure used in real estate development and construction lending that compares the size of a loan with the total cost of the project it funds. A lender that caps LTC at 65% will lend no more than 65% of the budgeted cost of land, construction and related expenses, leaving the developer to fund the rest with equity or junior capital. LTC is used by banks, debt funds and other lenders to commercial real estate and residential developers.
LTC is closely related to the loan-to-value ratio (LTV), which compares the loan with the property's appraised value rather than its cost. For a building that does not yet exist, cost is known with more certainty than value, so construction lenders usually apply both tests and lend the lower of the two results. LTC also shows how much of the developer's own money is at risk, which lenders see as an important source of alignment.
Formula and example
The standard calculation is:
Suppose a developer plans an apartment building with land costing $4 million, hard construction costs of $12 million, soft costs of $3 million and financing costs, including an interest reserve, of $1 million. Total project cost is $20 million. A senior loan of $13 million gives:
If the completed building is appraised at $26 million, the same loan has an LTV on completed value of 50%. The developer must fund the remaining $7 million of cost, 35% of the total, with equity or with mezzanine financing and preferred equity.
What counts as cost
The denominator normally includes all the money needed to complete the project:
- Land. The purchase price, usually at cost. If the developer has owned the land for years and it has risen in value, lenders differ on whether to credit the higher value as equity.
- Hard costs. Construction contracts, materials, labour and a contingency for overruns.
- Soft costs. Design, engineering, permits, legal fees, insurance, marketing and developer fees.
- Financing costs. Loan fees and the interest reserve that pays interest during construction, before the property earns income.
Because definitions vary, lenders specify in the loan agreement which costs are included and may exclude items such as developer profit or related-party fees.
Typical levels and the capital stack
Senior construction lenders commonly limit LTC to somewhere between about 60% and 75%, depending on the property type, market, sponsor and level of pre-sales or pre-leasing. Junior lenders may extend total leverage to a higher combined LTC, typically secured on the developer's ownership interests through a mezzanine real estate loan. Bank regulators also influence levels. In the United States, interagency real estate lending guidelines set supervisory loan-to-value limits for construction and land development loans, and higher-risk acquisition, development and construction lending attracts higher capital weights. In the United Kingdom, development lenders often quote loan-to-gross-development-value alongside LTC.
Once a project is complete and leased, the LTC test usually falls away and the loan is judged on value and income, often through a loan-to-value covenant in the permanent loan. Equity investors also use LTC to describe their exposure: a preferred equity provider funding the slice from 65% to 80% of cost is said to have a last-dollar exposure of 80% LTC, which gives a quick sense of how far costs or values can move before its capital is at risk.
Uses and limitations
Construction loans are drawn in stages as work progresses, with each draw checked by a monitoring surveyor or inspector against the budget. Lenders often require the developer's equity to be spent first, and a completion guarantee from the sponsor to cover overruns. As drawn amounts and costs change, the lender tests that the remaining loan and equity are enough to finish the project, a check sometimes called being in balance.
LTC has limits. A low ratio does not protect the lender if the finished building is worth less than it cost, which is why LTV and income tests such as projected debt yield on stabilised net operating income are applied alongside it. Cost overruns raise the denominator but must be funded by someone, usually the developer, and a budget that looks conservative at signing can be overtaken by inflation in materials and labour. A developer may also try to inflate the reported cost, for example through related-party fees, to obtain a larger loan, so lenders review budgets independently. Delays add to lease-up risk and to the risk of not being able to replace the construction loan with permanent refinancing or a bridge loan when it matures.