Provisional acceptance is the point in a construction, engineering or capital equipment contract at which the owner accepts the works or plant as substantially complete and takes them over, while some items remain to be finished or corrected. It typically follows mechanical completion and initial tests, and is recorded in a certificate listing the outstanding minor works and defects, often called a punch list. Some contracts use terms such as taking-over or substantial completion for the same stage.
Provisional acceptance usually triggers financial events: a further progress payment, release of part of the retention, reduction or return of the performance bond, the start of the warranty period and the transfer of risk to the owner. In export finance, it can mark the starting point of credit for repayment of a buyer credit. Final acceptance follows at the end of the warranty period, once all defects have been put right.