The percentage-of-completion method is an accounting method that recognizes revenue and profit on a long-term contract gradually, in step with progress, instead of waiting until the work is finished. It is a form of revenue recognition used by builders, shipyards and defense contractors whose projects span several reporting periods. Progress is most often measured cost-to-cost, so that . On a $10 million contract with $8 million of expected costs, $2 million spent means 25% completion and $2.5 million of revenue.
In the United States the method came from older construction-contract guidance, and under IFRS from IAS 11. Both were replaced by ASC 606 and IFRS 15, effective from 2018, which keep the idea as revenue recognized over time for a performance obligation. Progress is now measured by an input method, such as costs or labor hours, or an output method, such as units delivered or milestones reached. Revenue earned ahead of billing is shown as a contract asset.