The discounted payback period is a capital budgeting measure of how long an investment takes to recover its initial cost when future cash flows are converted to present value using a discount rate. It refines the simple payback period, which ignores the time value of money. For example, a project costing 1,000 that returns 500 a year for three years, discounted at 10%, has present values of about 454.5, 413.2 and 375.7. The first two years recover 867.8, so the remaining 132.2 is recovered about 0.35 of the way through year three, giving a discounted payback of roughly 2.35 years, against exactly 2 years on the simple measure.
Projects pass if discounted payback beats a target. The measure ignores cash flows after the payback point, so it can reject projects with large later returns; it is usually used alongside net present value (NPV) and the internal rate of return.