Cost escalation is the increase in the cost of particular inputs, such as steel, fuel, equipment or wages, between the time a price is agreed or a budget is set and the time the money is spent. It is narrower than general inflation: the prices relevant to a project can rise much faster or slower than a broad index such as the Consumer Price Index (CPI).
Long-term supply and construction contracts deal with escalation in several ways. A fixed price leaves the risk with the seller or contractor, who adds a margin for it. An escalation or price adjustment clause links part of the contract price to published indices, such as the Producer Price Index (PPI) or labour cost indices, so the buyer pays more if costs rise. Project budgets include an escalation allowance separate from the contingency for unforeseen events. Lenders in project finance test whether a project can absorb escalation before agreeing to fund it.