Completion risk is the risk that a project under construction is not completed on schedule, within budget or to the technical standard needed to operate as planned. In project finance, where loans are repaid only from the project's future cash flows, a project that is never finished, or finished late or underperforming, may not generate enough revenue to service its debt. It is usually seen as the most serious risk in a project's life.
The risk is typically allocated in layers. The construction contractor carries much of it under a fixed-price, date-certain EPC or turnkey contract, backed by delay and performance liquidated damages and a performance bond. Sponsors often provide a completion guarantee or other support, which makes the loan limited recourse until the project passes its completion test. Lenders add contingency budgets, standby funding and independent engineer reviews. Once completion is achieved, recourse usually falls away and the financing becomes non-recourse.